top of page

Project Updates

Below you will find the latest updates for projects in development and permitting. You can find more information about the different phases of development under Oil and Gas 101.  If you have additional questions, please reach out to us on the Oxy Response Line. Operational timeframes are impacted by various factors and are subject to change; we will keep you updated via this web page.

Locations Under Development

Mt. Democrat

Berry Farms: Our Estimated Interim Reclamation Period began in October 2023. Our Estimated Interim Reclamation Period is expected to conclude in July 2024.

Swartz: Surface Casing concluded in October 2023. Horizontal Drilling is expected to begin in April 2024.

Camenisch: Pad Construction concluded in October 2023. Surface Casing is expected to begin in April 2024.

North Core

Blue Chip: Our Estimated Interim Reclamation Period began in January 2024. Our Estimated Interim Reclamation Period is expected to conclude in October 2024.

Rainbow: Completions Activities concluded in February 2024. Our Estimated Interim Reclamation Period is expected to begin in May 2024.

Pikes Peak

Moser: Completions Activities began in January 2024. Facilities Construction is expected to conclude in February 2024.

Wardell: Completions Activities began in January 2024. Facilities Construction is expected to conclude in March 2024.

Hethcock: Facilities Construction began in January 2024. Completions Activities are expected to begin in March 2024.

Land Fed

Facilities Construction concluded in January 2024. Completions Activities are expected to conclude in March 2024.

Flower

We have completed the local and state permitting processes. Details on the project can be found in the Completeness notice to the right.

Schmerge: There has been a slight shift to the schedule. Pad Construction is now scheduled to begin in March 2024.

Vista: Pad Construction has been completed. Drilling is expected to begin in March 2024.

Lizzy

The pad has been constructed, and drilling has begun. This phase of the project is expected to continue into late spring 2024.

Salazar

Pad Construction concluded in January 2024. Horizontal Drilling is expected to begin in February 2024.

Important Links

Oct 2023 - Salazar Drilling & Pad Construction Notice

Aug 2023 - Salazar Completeness Notice

Feb 2023- Salazar Weld County Permit Notice

Labrisa

Facilities Construction began in February 2024. Horizontal Drilling is expected to conclude in March 2024.

Fort Lupton: Griswold

The regulatory processes are complete, and on site has begun. For more information on the project, please see the links to the right or contact a member of our Stakeholder Relations team.

Locations in Planning and Permitting

Oak: Alder and Acacia

We are currently working through state and local permitting processes. We will provide further details on operational activities if the projects are approved.

Cypress

We continue to work through the state and local permitting processes. The Energy and Carbon Management Commission has determined the application to be complete and has scheduled a hearing for late January 2024.

Hickory

We are working through the state and local permitting processes. We will provide further details on the progression of the permit.

Locations Previously Developed

Jodster

You may have received information about this area being evaluated for a proposed project. If you live nearby and would like to provide feedback, please feel free to contact a member of our stakeholder relations team. 

Important Links

Apr 2023 - MLVT

Project Archives


View the project archives for wells that are producing.

bottom of page