Project Updates
Below you will find the latest updates for projects in development and permitting. You can find more information about the different phases of development under Oil and Gas 101.
If you have additional questions, please reach out to us on the Oxy Response Line. Operational timeframes are impacted by various factors and are subject to change; we will keep you updated via this web page.
Locations Under Development
TULIP
We have permit approval from both state and local agencies. Pad construction is expected to begin soon.
LARKSPUR FED
We are currently constructing the location, with initial drilling activity planned to start in early 2025.
FILLY
This project has been fully approved and is expected to begin development in 2025. See the Bronco CAP website for more information.
HICKORY
We are currently constructing the location, with initial drilling activity planned to start in early 2025.
SPROUT
We have achieved permit approval from both state and local agencies.
Rademacher: This location has been turned over to production as of November 2024.
Clover: The location is currently being drilled, with plans to complete the drilling phase by late December 2024.
Alfalfa: The location is currently being drilled, with plans to complete the drilling phase by late December 2024.
Important Links
October 2024 - Air Monitoring Summary (R)
October 2024 - Air Monitoring Summary (C)
October 2024 - Completions Notice (C)
August 2024 - Air Monitoring Notice (R)
July 2024 - Air Monitoring Notice (R)
July 2024 - Completions Notice (R)
August 2024 - Drilling & Pad Construction Notice (A)
June 2024 - Drilling & Pad Construction Notice (C)
March 2024 - Drilling & Pad Construction Notice (R)
December 2023 - Sprout Completeness Notice
December 2023 - Sprout Community Meeting Poster Slides
November 2023 - Community Meeting Invite
November 2023 - Community Meeting Invite (C)
November 2023 - Community Meeting Invite (A)
June 2023 - Weld County Permit Notice (A)
OAK
We have permit approval from both state and local agencies.
Alder: We have achieved state and local permits for this location. Initial construction and drilling activity is currently planned summer of 2025.
Acacia: The location is built, and initial drilling activity is planned to start early December 2024.
Mt. DEMOCRAT
Berry Farms: This location is currently operational.
Swartz: This location was turned over to production in early November 2024 and is currently operational.
Camenisch: This location was turned over to production in early November 2024 and is currently operational.
Important Links
October 2024 - Air Monitoring Summary (S)
October 2024 - Air Monitoring Summary (C)
July 2024 - Completions Notice (C)
May 2024 - Completions Notice (S)
June 2023 - Completeness Notice (C)
March 2023 - Drilling & Pad Construction (S)
March 2023 - Completions Notice (B)
September 2022 - Drilling & Pad Construction (B)
June 2022 - Completeness Notice (English)
June 2022 - Completeness Notice (Spanish)
November 2021 - Weld County Permit Notice (S)
November 2021 - Weld County Permit Notice (C)
FLOWER
Schmerge: Completions activities are expected to start in early January and expected to end in Mid-March 2025.
Vista: Completions activities are finished. Reclamation will begin in the coming weeks.
Important Links
October 2024 - Air Monitoring Summary (S)
October 2024 - Air Monitoring Summary (V)
September 2024 - Air Monitoring Summary (V)
September 2024 - Air Monitoring Summary (S)
October 2024 - Completions Notice (S)
August 2024 - Air Monitoring Notice (S)
August 2024 - Air Monitoring Notice (V)
July 2024 - Air Monitoring Notice (V)
June 2024 - Air Monitoring Summary (V)
June 2024 - Completions Notice (V)
January 2024 - Drilling & Pad Construction Notice (S)
October 2023 - Drilling & Pad Construction Notice (V)
September 2023 - Drilling & Pad Construction Notice (S)
LIZZY
Completions activities will begin in early December 2024 and estimated to end in Mid-January 2025.
Important Links
October 2024 - Air Monitoring Summary
September 2024 - Air Monitoring Summary
September 2024 - Completions Notice
August 2024 - Air Monitoring Notice
July 2024 - Air Monitoring Notice
June 2024 - Air Monitoring Summary
February 2024 - Air Monitoring Summary
January 2024 - Air Monitoring Summary
December 2023 - Air Monitoring Summary
SALAZAR
Completions activities are currently underway, with an expected finish in early December 2024.
Important Links
October 2024 - Air Monitoring Summary
August 2024 - Completions Notice
April 2024 - Air Monitoring Summary
October 2023 - Drilling & Pad Construction Notice
August 2023 - Completeness Notice
February 2023 - Weld County Permit Notice
GRISWOLD ENHANCED OIL RECOVERY TEST
Griswold: Various construction work continues and is expected to continue intermittently through December 2024.
Locations in Planning and Permitting
MAGNOLIA
We continue to work with state and local regulatory agencies to permit this location. Please reach out for more details about this upcoming project.
WISHBONE
This project has been postponed to early January 2025.
MESQUITE
We continue to work with state and local regulatory agencies to permit this location. Please reach out for more details about this upcoming project.
INDIGO
We continue to work with state and local regulatory agencies to permit this location. Please reach out for more details about this upcoming project.
FERN
We continue to work with state and local regulatory agencies to permit this location. Please reach out for more details about this upcoming project.
PARSNIP FED
We recently held a pre-application community meeting and have submitted a permit application to the state for review. We will hold another community meeting in the coming months. Please reach out to a member of our team for more information.
GEOTHERMAL PILOT PROJECT
Geothermal energy is a form of renewable energy derived from the heat stored beneath the earth's surface. We are planning on using our industry-leading expertise in drilling and carbon management to work towards Net Zero emissions goals. Oxy is working through the permitting process on a geothermal project in your community. The two-well project requires permits from both the Colorado Energy and Carbon Management Commission (ECMC) and Weld County. The ECMC has determined the application is complete. At this time, we estimate that drilling will start in 2025. The timeline for development is based on obtaining the required permits and drilling rig availability.
CYPRESS
We continue to work through the state and local permitting processes. The Energy and Carbon Management Commission has determined the application to be complete. The hearing date is TBD.