top of page

Project Updates

Below you will find the latest updates for projects in development and permitting. You can find more information about the different phases of development under Oil and Gas 101

 

If you have additional questions, please reach out to us on the Oxy Response Line. Operational timeframes are impacted by various factors and are subject to change; we will keep you updated via this web page.

Locations Under Development

FILLY 

There is an upcoming ECMC hearing on August 14th, 2024. This Comprehensive Area Plan (CAP) was previously approved. See the Bronco CAP website. 

Important Links

See the Bronco CAP webpage

HICKORY

We have achieved permit approval from both state and local agencies. Initial work and pad construction is currently planned for January 2025. 

SPROUT

We have achieved permit approval from both state and local agencies. 

Rademacher: We are currently starting completion activities on a portion of the wells, expected to conclude mid-November 2024.

Clover: The location is built, and we are currently  starting initial drilling activity at this location.

 

Alfalfa: Initial drilling activities are currently planned for later October 2024.

OAK: Alder and Acacia

We have permit approval from both state and local agencies.

 

Acacia: Pad construction on this location is scheduled to begin in the summer of 2024.

Mt. DEMOCRAT

Berry Farms: This location is currently operational.

Swartz: Completion activities continue at this location, with an expected end date of early November 2024.

Camenisch: Completion activities continue at this location, with an expected end date of early November 2024.

NORTH CORE

Blue Chip: All major operations have been completed. Periodic work will take place as  reclamation continues. Please connect with a member of our Stakeholder Relations team if you have specific questions.
Rainbow:  A smaller rig will be performing work through the third week in July and crews will not be back until the end of the year.
PIKES PEAK

Moser Fed: Completion activities have completed late Summer 2024.

Wardell Fed: Completion activities have completed late Summer 2024.

Hethcock Fed: Completion activities have completed late Summer 2024.

LIZZY 

The first portion of drilling has finished. Crews will continue to be onsite to wrap up completions activities for the first portion of the project and will begin drilling the second portion in August.
SALAZAR

Completion activity is planned for mid-October, with an expected finish date of the end of 2024.

GRISWOLD ENHANCED OIL RECOVERY TEST

Griswold: Various construction work continues and is expected to continue intermittently through December 2024.

Locations in Planning and Permitting

LARKSPUR FED

We have received approval from local agencies and a have now submitted the permit for state-level approval.

GEOTHERMAL PILOT PROJECT

Geothermal energy is a form of renewable energy derived from the heat stored beneath the earth's surface. We are planning on using our industry-leading expertise in drilling and carbon management to work towards Net Zero emissions goals. Oxy is working through the permitting process on a geothermal project in your community. The two-well project requires permits from both the Colorado Energy and Carbon Management Commission (ECMC) and Weld County. The ECMC has determined the application is complete. At this time, we estimate that drilling will start in 2025. The timeline for development is based on obtaining the required permits and drilling rig availability.

TULIP

We continue to work through the permitting process and are looking forward to connecting with you at our virtual community meeting in the coming weeks. Please click the "September 2024 - Tulip Virtual Meting" link for details.

CYPRESS

We continue to work through the state and local permitting processes. The Energy and Carbon Management Commission has determined the application to be complete and has scheduled a hearing for September 2024.

Locations Previously Developed

STATE OF COLORADO AZ1 FLOWLINE REMOVAL

While completing reclamation activities at the former St of Colo AL2 & AL1 O SA facility, Kerr McGee Oil & Gas Onshore LP (KMOG) discovered several abandoned subsurface lines that formerly transported crude oil and produced water between equipment within the facility. Stained soil was also observed near the lines. Soil samples were collected and detections above the Energy and Carbon Management Commission (ECMC) standards for hydrocarbons were identified. KMOG has reported these detections to the ECMC through a Form 19 Spill/Release Report. The abandoned lines are in the process of being removed. Once the lines are removed, and in accordance with ECMC regulations, the impacted soil will be excavated and taken to a licensed disposal facility. Additional soil samples will be collected to confirm the impacts have been removed, and clean fill material will be brought in to backfill the excavation. These cleanup efforts will be documented in a supplemental Form 19 Spill/Release Report.

The Oxy Stakeholder Relations team is a dedicated resource for community members. Please contact us if you have any questions or comments about our operations. You can reach our team at 866.248.9577, ColoradoStakeholder@oxy.com.

If you have an urgent concern and it is after regular business hours, please reach out to the Integrated Operations Center 970.515.1500

PROJECT ARCHIVES

View the project archives for wells that are producing.

bottom of page